A Realistic Schedule for Your Kitchen Remodel

A Realistic Schedule for Your Kitchen Remodel

With projects like kitchen and bathroom remodeling, where a critical part of your home will be under construction for a period of time, the project timeline is always a concern. Having a detailed conversation with your contractor about this subject ahead of time helps to set expectations and reduce stress along the way.

A Realistic Schedule for Your Kitchen Remodel

Today, Northside Construction Services shares a realistic timeline for a typical kitchen remodel.

Removal of Existing Kitchen

The existing kitchen needs to be stripped completely bare before anything else can happen. This process usually takes two to three days. The demolition involves the removal of existing cabinets, countertops, flooring and appliances. If there will be changes to your exterior walls or there’s a need for home repair, this phase will take longer.

Marking Location of Electrical Outlets, Fixtures and Appliances

Your contractor needs to mark various spaces in your kitchen. This will guide them during the various installations and helps ensure that the power outlets are all in the right places. This step takes about a day to be completed.

Mechanicals Installation

Your contractor will spend an average of five days to set up your new plumbing, electrical and HVAC systems.

Insulation, Drywall and Flooring

At this stage of the project, your kitchen is insulated and the drywall is prepped, installed, and primed. Next, the flooring will be installed. The timeline for this part of the project will vary depending on what materials you choose.

Cabinets and Countertops Installation

This is the most exciting phase for most homeowners. With the installation of cabinets and countertops, the final look of your new kitchen begins to emerge. However, installing countertops can take a while. For instance, the fabrication process of granite countertops is usually completed in approximately 10 days.

Electrical Fixtures and Appliances Installation

This is usually the final stage of a kitchen remodel, and it takes about two days to be finished. This is when small touch-ups and fine-tuning are done.

Northside Construction Services performs a variety of home remodeling jobs including basement finishing, bathroom and kitchen remodels, and minor repairs. Call us at (678) 233-2400 or fill out our contact form to request a free estimate. We serve customers in Evans and Augusta, GA.